Switch - RNO 5 - 公共プロジェクト現場
-
29th 9月 2026, RNO 05 Cloud 4 Hydro test 9/30/26 UPDATED
Contractor: ACCO Mechanical
Location: Cloud 4 including fan galleries
System: HAC Manifold, SFN
Test Pressure: 150 PSI Hydro
Exclusion Zone: 1 foot
Date: Hydro 9/30/26
Time: Monday 6:00am to 2:00pm
Test Details
All,
ACCO will be performing a hydro in the north & south loop of the SFN piping; all access to the areas will be limited until the hydro test is completed.
Please observe all posted barriers & contact Giovanni Pirrodi (775-432-9183) if you need to enter the exclusion zone
Safety & Coordination:
For the safety of all personnel and to minimize disruptions, please ensure that all trades coordinate with onsite teams to relocate work activities away from the designated testing area during the specified time.
Thank you for your cooperation. -
29th 9月 2026, RNO5 J-Line Shutdown COSCO Pipe Install 9/30/26
All,
添付ファイル :
Cosco will continue installing 2-inch pipe along J-Line
As work progresses from west to east, small sections of the J-Line corridor will be temporarily closed. Please plan accordingly and use alternate routes when necessary.
For everyone's safety, please:
-Observe all barricades, signage, and designated pedestrian walkways.
-Do not enter restricted work areas unless authorized.
-Maintain situational awareness when moving through or around the work zone.
Cosco J-Line Work access .png
-
04th 9月 2026, SITE WEATHER NOTIFICATION – HIGH WINDS
SITE WEATHER NOTIFICATION – HIGH WINDS
Current Wind: 27 MPH
Wind speeds have exceeded the site’s 23 MPH threshold.
Cranes & material platforms: Shut down.
MEWPs/outdoor work: Evaluate with Gray Safety.
Roof work/access: Stop work.
Secure loose materials and equipment.
Continue monitoring wind conditions and follow Gray Safety direction.
現在の現場の天気
利用できません
タイムゾーン - アメリカ東部標準時
予測 - 土曜日, 10 10月
利用できません
明日 - 日曜日, 11 10月
利用できません