Switch - RNO 5 - Cantiere del progetto pubblico
-
24th marzo 2026, Break Tent Service
Sunbelt to service break tent south at 6:45am and New tent at 7:45am
about a 30 minute to 45 minute down time. -
18th marzo 2026, RNO4 Fire Protection Systems Going Live
Team,
For everyone's awareness there is a final TCO Inspection today with the Fire Marshall at 15:00 for clouds 3 & 4 and power rooms 3 & 4. After said inspection systems will be fully live in a permanent state moving forward.
Again, this is for clouds 300 400 and the associated power rooms in RNO4 - please treat these as live systems moving forward. -
04th marzo 2026, RNO 4,5 & 6 Exterior Work
Teams, all exterior work is open back up for work. We will continue to monitor and notify if conditions change.
Meteo attuale del cantiere
Non disponibile
Fuso orario - Ora standard orientale USA
Previsioni - giovedì, 2 aprile
Non disponibile
Domani - venerdì, 3 aprile
Non disponibile
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.