Switch - RNO 5 - Sitio de proyecto público
-
24th marzo 2026, Break Tent Service
Sunbelt to service break tent south at 6:45am and New tent at 7:45am
about a 30 minute to 45 minute down time. -
18th marzo 2026, RNO4 Fire Protection Systems Going Live
Team,
For everyone's awareness there is a final TCO Inspection today with the Fire Marshall at 15:00 for clouds 3 & 4 and power rooms 3 & 4. After said inspection systems will be fully live in a permanent state moving forward.
Again, this is for clouds 300 400 and the associated power rooms in RNO4 - please treat these as live systems moving forward. -
04th marzo 2026, RNO 4,5 & 6 Exterior Work
Teams, all exterior work is open back up for work. We will continue to monitor and notify if conditions change.
Tiempo en Obra actual
No disponible
Zona horaria - hora estándar oriental
Pronóstico - jueves, 2 abril
No disponible
Mañana - viernes, 3 abril
No disponible
¿Conoce los requisitos de PPE para esta Obra?
Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.
Empiece a trabajar en cuanto llegue a la obra.
Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.
¿Conoce los requisitos de PPE para esta Obra?
Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.
Empiece a trabajar en cuanto llegue a la obra.
Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.