Switch - RNO 5 - Public Project Site
-
24th March 2026, Break Tent Service
Sunbelt to service break tent south at 6:45am and New tent at 7:45am
about a 30 minute to 45 minute down time. -
18th March 2026, RNO4 Fire Protection Systems Going Live
Team,
For everyone's awareness there is a final TCO Inspection today with the Fire Marshall at 15:00 for clouds 3 & 4 and power rooms 3 & 4. After said inspection systems will be fully live in a permanent state moving forward.
Again, this is for clouds 300 400 and the associated power rooms in RNO4 - please treat these as live systems moving forward. -
04th March 2026, RNO 4,5 & 6 Exterior Work
Teams, all exterior work is open back up for work. We will continue to monitor and notify if conditions change.
Current Site Weather
Unavailable
Time Zone - Eastern Standard Time
Forecast - Thursday, 2 April
Unavailable
Tomorrow - Friday, 3 April
Unavailable
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Complete your site registration online at your convenience and save yourself time.
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Complete your site registration online at your convenience and save yourself time.