QTS - NAL2 DC1
Bollettini recenti
  • 14th luglio 2025,

    All
    We will be energizing Pods A-R2100 at DC2 at 7am on Tuesday 07.015.25. the North side of the Gen yard and the west corridor will be shut down to unauthorized personnel during energization. Please adhere to all CAZs, Signage and barricades.

  • 10th luglio 2025, Lightning standown

    Lightning is 3 miles out. All exterior work must stop. Please monitor group me for when the lightning subsides. Must be over 6 miles away for exterior ground work and over 10 for elevated exterior work.

  • 01st luglio 2025, 24-48 hour energization notice

    All

    We will be energizing HSE-SWR (house switch gear) on 07.02.25 at 11am in DC1. All unauthorized personnel must vacate the area. Please pay attention to all signage, barricades, and CAZs

Previsioni meteo del cantiere
Meteo attuale del cantiere

Non disponibile


Osservazione proveniente da - Non disponibile
Fuso orario - Ora standard orientale USA
Previsioni - giovedì, 17 luglio

Non disponibile


Fuso orario - Ora standard orientale USA
Domani - venerdì, 18 luglio

Non disponibile


Documenti importanti per il cantiere
Nuovo sul cantiere?

Conosci i requisiti dei DPI per questo cantiere?

Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.

Visualizza requisiti DPI del cantiere

Inizia a lavorare prima quando arrivi sul cantiere.

Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.

Inizio registrazione

Nuovo sul cantiere?

Conosci i requisiti dei DPI per questo cantiere?

Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.

Visualizza requisiti DPI del cantiere

Nuovo sul cantiere?

Inizia a lavorare prima quando arrivi sul cantiere.

Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.

Inizio registrazione