QTS - NAL2 DC1 - Cantiere del progetto pubblico
-
14th luglio 2025,
All
We will be energizing Pods A-R2100 at DC2 at 7am on Tuesday 07.015.25. the North side of the Gen yard and the west corridor will be shut down to unauthorized personnel during energization. Please adhere to all CAZs, Signage and barricades. -
10th luglio 2025, Lightning standown
Lightning is 3 miles out. All exterior work must stop. Please monitor group me for when the lightning subsides. Must be over 6 miles away for exterior ground work and over 10 for elevated exterior work.
-
01st luglio 2025, 24-48 hour energization notice
All
We will be energizing HSE-SWR (house switch gear) on 07.02.25 at 11am in DC1. All unauthorized personnel must vacate the area. Please pay attention to all signage, barricades, and CAZs
Meteo attuale del cantiere
Non disponibile
Fuso orario - Ora standard orientale USA
Previsioni - giovedì, 17 luglio
Non disponibile
Domani - venerdì, 18 luglio
Non disponibile
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.