QTS - NAL2 DC1 - Offentlig projektarbejdsplads
-
11th september 2025, 24-48 hour Energization
Team
We will be energizing Crac Units 1200 1-25 and the reserve bus today in the 1100 and 1200 gallerys. Please adhere to all safety procedures, signage, barricades & signage that will restrict access to these areas. -
09th september 2025, 24-48 hour energization
All
We will be energizing 1200 STSs at 4:30pm today 09.09.25 in the west gallery 2nd level. Area will be barricaded and only qualified personnel will be allowed in the work area. all work to resume after energization. -
05th september 2025, Cosco RNO 5 Fire Suppression Testing
Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.
Vedhæftede filer :
Power room 4 5 6 .pdf
Aboveground Test Cert copy .pdf
IMG_0383.jpg
Switch5 system 5&6.pdf
System 14.pdf
Aktuelt vejr på stedet
Utilgængelig
Tidszone - Eastern-normaltid
Prognose - søndag, 14 september
Utilgængelig
Imorgen - mandag, 15 september
Utilgængelig
Kender du kravene for personlige værnemidler til dette sted?
Sørg for, at du har det korrekte sikkerhedsudstyr til din første dag på arbejdspladsen.
Kom hurtigere i gang med arbejdet, når du ankommer til stedet.
Afslut din webstedsregistrering online, når det passer dig, og spar tid.
Kender du kravene for personlige værnemidler til dette sted?
Sørg for, at du har det korrekte sikkerhedsudstyr til din første dag på arbejdspladsen.
Kom hurtigere i gang med arbejdet, når du ankommer til stedet.
Afslut din webstedsregistrering online, når det passer dig, og spar tid.