QTS - NAL2 DC1 - Εργοτάξιο δημόσιου έργου
-
11th Σεπτεμβρίου 2025, 24-48 hour Energization
Team
We will be energizing Crac Units 1200 1-25 and the reserve bus today in the 1100 and 1200 gallerys. Please adhere to all safety procedures, signage, barricades & signage that will restrict access to these areas. -
09th Σεπτεμβρίου 2025, 24-48 hour energization
All
We will be energizing 1200 STSs at 4:30pm today 09.09.25 in the west gallery 2nd level. Area will be barricaded and only qualified personnel will be allowed in the work area. all work to resume after energization. -
05th Σεπτεμβρίου 2025, Cosco RNO 5 Fire Suppression Testing
Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.
Προσαρτήματα :
Power room 4 5 6 .pdf
Aboveground Test Cert copy .pdf
IMG_0383.jpg
Switch5 system 5&6.pdf
System 14.pdf
Ο καιρός στο τρέχων εργοτάξιο
Μη διαθέσιμο
Ζώνη ώρας - Ανατολική χειμερινή ώρα Βόρειας Αμερικής
Πρόγνωση - Κυριακή, 14 Σεπτεμβρίου
Μη διαθέσιμο
Αύριο - Δευτέρα, 15 Σεπτεμβρίου
Μη διαθέσιμο
Γνωρίζετε τις προδιαγραφές των ΜΑΠ για το συγκεκριμένο εργοτάξιο;
Βεβαιωθείτε ότι έχετε τον κατάλληλο εξοπλισμό ασφαλείας για την πρώτη ημέρα σας στο εργοτάξιο.
Προβολή ΜΑΠ (Μέσα Ατομικής Προστασίας) που Απαιτούνται στην Εργασία
Ξεκινήστε να εργάζεστε συντομότερα όταν φτάνετε στο εργοτάξιο.
Ολοκληρώστε την καταχώρηση του εργοταξίου σας διαδικτυακά, με την άνεσή σας και εξοικονομήστε χρόνο.
Γνωρίζετε τις προδιαγραφές των ΜΑΠ για το συγκεκριμένο εργοτάξιο;
Βεβαιωθείτε ότι έχετε τον κατάλληλο εξοπλισμό ασφαλείας για την πρώτη ημέρα σας στο εργοτάξιο.
Προβολή ΜΑΠ (Μέσα Ατομικής Προστασίας) που Απαιτούνται στην Εργασία
Ξεκινήστε να εργάζεστε συντομότερα όταν φτάνετε στο εργοτάξιο.
Ολοκληρώστε την καταχώρηση του εργοταξίου σας διαδικτυακά, με την άνεσή σας και εξοικονομήστε χρόνο.