QTS - NAL2 DC1 - Public Project Site
-
14th July 2025,
All
We will be energizing Pods A-R2100 at DC2 at 7am on Tuesday 07.015.25. the North side of the Gen yard and the west corridor will be shut down to unauthorized personnel during energization. Please adhere to all CAZs, Signage and barricades. -
10th July 2025, Lightning standown
Lightning is 3 miles out. All exterior work must stop. Please monitor group me for when the lightning subsides. Must be over 6 miles away for exterior ground work and over 10 for elevated exterior work.
-
01st July 2025, 24-48 hour energization notice
All
We will be energizing HSE-SWR (house switch gear) on 07.02.25 at 11am in DC1. All unauthorized personnel must vacate the area. Please pay attention to all signage, barricades, and CAZs
Current Site Weather
Unavailable
Time Zone - Eastern Standard Time
Forecast - Wednesday, 16 July
Unavailable
Tomorrow - Thursday, 17 July
Unavailable
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enroll online at your convenience and save yourself time.
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enroll online at your convenience and save yourself time.