QTS - NAL2 DC1 - सार्वजनिक प्रोजेक्ट साइट
-
11th सितम्बर 2025, 24-48 hour Energization
Team
We will be energizing Crac Units 1200 1-25 and the reserve bus today in the 1100 and 1200 gallerys. Please adhere to all safety procedures, signage, barricades & signage that will restrict access to these areas. -
09th सितम्बर 2025, 24-48 hour energization
All
We will be energizing 1200 STSs at 4:30pm today 09.09.25 in the west gallery 2nd level. Area will be barricaded and only qualified personnel will be allowed in the work area. all work to resume after energization. -
05th सितम्बर 2025, Cosco RNO 5 Fire Suppression Testing
Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.
अटैचमेंट :
Power room 4 5 6 .pdf
Aboveground Test Cert copy .pdf
IMG_0383.jpg
Switch5 system 5&6.pdf
System 14.pdf
साइट का मौजूदा मौसम
उपलब्ध नहीं है
समय क्षेत्र - उत्तरी अमेरिकी पूर्वी मानक समय
पूर्वानुमान - रविवार, 14 सितम्बर
उपलब्ध नहीं है
कल - सोमवार, 15 सितम्बर
उपलब्ध नहीं है
क्या आप इस साइट के लिए आवश्यक PPE के बारे में जानते हैं?
सुनिश्चित करें कि आपके पास साइट पर पहले दिन के लिए सही सुरक्षा इक्विपमेंट हैं।
जब आप साइट पर पहुंचें, तो जल्द से जल्द काम करना शुरू कर दें।
अपनी सुविधा के अनुसार अपना साइट रजिस्ट्रेशन ऑनलाइन पूरा करें और अपना समय बचाएँ।
क्या आप इस साइट के लिए आवश्यक PPE के बारे में जानते हैं?
सुनिश्चित करें कि आपके पास साइट पर पहले दिन के लिए सही सुरक्षा इक्विपमेंट हैं।
जब आप साइट पर पहुंचें, तो जल्द से जल्द काम करना शुरू कर दें।
अपनी सुविधा के अनुसार अपना साइट रजिस्ट्रेशन ऑनलाइन पूरा करें और अपना समय बचाएँ।