11th September 2025, 24-48 hour Energization
Team
We will be energizing Crac Units 1200 1-25 and the reserve bus today in the 1100 and 1200 gallerys. Please adhere to all safety procedures, signage, barricades & signage that will restrict access to these areas. -
09th September 2025, 24-48 hour energization
All
We will be energizing 1200 STSs at 4:30pm today 09.09.25 in the west gallery 2nd level. Area will be barricaded and only qualified personnel will be allowed in the work area. all work to resume after energization. -
05th September 2025, Cosco RNO 5 Fire Suppression Testing
Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.
Attachments :
Power room 4 5 6 .pdf
Aboveground Test Cert copy .pdf
IMG_0383.jpg
Switch5 system 5&6.pdf
System 14.pdf
Current Site Weather
Unavailable
Time Zone - Eastern Standard Time
Forecast - Sunday, 14 September
Unavailable
Tomorrow - Monday, 15 September
Unavailable
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enrol online at your convenience and save yourself time.
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enrol online at your convenience and save yourself time.