Maruchan - 公共项目现场
-
01st 七月 2025, Extension Ladders
Gray Practices a “ladders last” policy. Extension ladders are only to be used if all other means of getting to elevated work are not unfeasible.
附件 :
Ladders shall be inspected before each use by a competent person to check for missing rungs, bolts, cleats, screws, and loose components. Where a ladder has these or other defects, it must be immediately marked as defective or tagged with “Do Not Use” or similar language.
All ladders should be fit for the task at hand and rated for the correct weight with a legible sticker on that is visible.
A Ladder should be used at a 4:1 angle; for every 4 feet in height, the bottom of the ladder is 1 foot out. Extended 42” above the landing, on Gray’s site.
Ladders should be secured at top and bottom to prevent accidental displacement.
Workers should not carry any objects when climbing; use a tagline to raise or lower loads. Make sure any overhead work is barricaded, or a spotter is present.
Safety Moments Maruchan 7-1-25.pdf
-
16th 五月 2025, Energization
Phase 9 081
DAHA’s ; EF ; PDC’s CPP panels -
25th 四月 2025, 48 hour MVG 01/04 Energization
All
This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project.
当前现场天气
不可用
时区 - 北美太平洋标准时间
预测 - 星期五、4 七月
不可用
明天 - 星期六, 5 七月
不可用