18th Poutūterangi 2026, RNO4 Fire Protection Systems Going Live
Team,
For everyone's awareness there is a final TCO Inspection today with the Fire Marshall at 15:00 for clouds 3 & 4 and power rooms 3 & 4. After said inspection systems will be fully live in a permanent state moving forward.
Again, this is for clouds 300 400 and the associated power rooms in RNO4 - please treat these as live systems moving forward. -
12th Kohitātea 2026, SITE CLOSED Jan 19th & Feb 16th
Everybody,
On January 19th & February 16th the site will be shut down. -
15th Hakihea 2025, Extension Cords
Everybody,
- Over the past week I have removed multiple extension Cord due to damage
-Electricity is a fatal 4 in Construction so this is something we need to nip in the butt
-Before and after your shift communicate with your guys that extension cord are to be inspected & tagged out/ removed from the job if damaged.
Huarere Paemahi Onāianei
Korewātea
Rohe Wā - Wā Arowhānui Kiwa
Matapae - Rāpare, 2 Paengawhāwhā
Korewātea
Āpōpō - Rāmere, 3 Paengawhāwhā
Korewātea
E mōhio ana rānei koe ki ngā Whakaritenga PPE mō tēnei paemahi?
Āta tiaki kei a koe ngā taputapu haumarutanga tika mō tō rā tuatahi i te paemahi.
Tīmata wawe ake ina tae koe ki te paemahi.
Whakaotia tuihonotia tō rēhitatanga paemahi ina pai koe hei penapena tāima.
E mōhio ana rānei koe ki ngā Whakaritenga PPE mō tēnei paemahi?
Āta tiaki kei a koe ngā taputapu haumarutanga tika mō tō rā tuatahi i te paemahi.
Tīmata wawe ake ina tae koe ki te paemahi.
Whakaotia tuihonotia tō rēhitatanga paemahi ina pai koe hei penapena tāima.