18th marts 2026, RNO4 Fire Protection Systems Going Live
Team,
For everyone's awareness there is a final TCO Inspection today with the Fire Marshall at 15:00 for clouds 3 & 4 and power rooms 3 & 4. After said inspection systems will be fully live in a permanent state moving forward.
Again, this is for clouds 300 400 and the associated power rooms in RNO4 - please treat these as live systems moving forward. -
12th januar 2026, SITE CLOSED Jan 19th & Feb 16th
Everybody,
On January 19th & February 16th the site will be shut down. -
15th december 2025, Extension Cords
Everybody,
- Over the past week I have removed multiple extension Cord due to damage
-Electricity is a fatal 4 in Construction so this is something we need to nip in the butt
-Before and after your shift communicate with your guys that extension cord are to be inspected & tagged out/ removed from the job if damaged.
Aktuelt vejr på stedet
Utilgængelig
Tidszone - Pacific-normaltid
Prognose - torsdag, 2 april
Utilgængelig
Imorgen - fredag, 3 april
Utilgængelig
Kender du kravene for personlige værnemidler til dette sted?
Sørg for, at du har det korrekte sikkerhedsudstyr til din første dag på arbejdspladsen.
Kom hurtigere i gang med arbejdet, når du ankommer til stedet.
Afslut din webstedsregistrering online, når det passer dig, og spar tid.
Kender du kravene for personlige værnemidler til dette sted?
Sørg for, at du har det korrekte sikkerhedsudstyr til din første dag på arbejdspladsen.
Kom hurtigere i gang med arbejdet, når du ankommer til stedet.
Afslut din webstedsregistrering online, når det passer dig, og spar tid.