10th September 2025, (CO) Hazards and Safety Protocols Maruchan
All,
Attachments :
Take a moment to review the attached document regarding carbon monoxide (CO) hazards and safety protocols. Note that most gas monitoring devices are set to factory settings and may need to be adjusted to meet our site standards.
General Gas Monitoring
• CO at 50ppm: When the monitor detects 50ppm, implement additional measures:
o Use displacement fans inside the building.
o Remove combustion-powered equipment from the building, such as:
Welding machines
Boom lifts
Gas-powered equipment
Ect…
o If a subcontractor wants to utilized gas monitoring the following needs to be in place. This is for non-confined space activities.
Loggers name
Quad monitor Type:
Quad monitor Calibrations Date:
Time of the event:
Location of the active readings:
CO Readings at time of the evacuation:
Chart of Active Read:
• CO at 200ppm: Evacuate the building until CO levels drop below 50ppm.
Please remember that symptoms can occur at CO levels between 200ppm and 400ppm, similar to placing your face near an exhaust pipe.
Carbon Monoxide (CO) Hazard - Protocal_.pdf
-
05th September 2025, Cosco RNO 5 Fire Suppression Testing
Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.
Attachments :
Power room 4 5 6 .pdf
Aboveground Test Cert copy .pdf
IMG_0383.jpg
Switch5 system 5&6.pdf
System 14.pdf
-
03rd September 2025, RNO4 Area L Power Rooms Pressure Test 9/3/25
All - Please see below details for ACCO Pressure test to take place in RNO4 tomorrow 9/3/25.
Attachments :
Location: RNO4 Sector L Power Rooms (Vaults 7 & 8)
System: 10" Chilled Water Piping
Pressure: 150 PSI Hydrostatic
Test Duration: 3 hours (1 hour fill 2 hours test)
Exclusion zone will only prohibit work taking place above 10' from finished floor.
Exclusion starts: 9/3/2025 3:00PM
Exclusion expected end: 9/3/25 6:00PM
Sector L Test #L1 10 inch Markup Power Rooms.pdf
Current Site Weather
Unavailable
Time Zone - Pacific Standard Time
Forecast - Sunday, 14 September
Unavailable
Tomorrow - Monday, 15 September
Unavailable
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enrol online at your convenience and save yourself time.
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enrol online at your convenience and save yourself time.