Amazon 1DC OH
近期公告
  • 29th 八月 2026, Nitrogen Pressure-Testing Plug Power H2 Dispensers Amazon OH 1DC 9am-6pm

    o Testing duration is expected to be 8 hours, starting at 0900 AM
    o All system tubing is 0.38” x 0.065” wall, 0.245 inner diameter.
    o Target test pressure is 7,180 psi
    o Areas being tested and exclusion zones (zones determined using Gray’s safe distance calculator):
     Outdoor hydrogen transfer station (HTS) and field manifold
    • 80’ exclusion zone
    o Danger tape cordon with appropriate signage around perimeter
     Roof area
    • 80’ exclusion zone
    o Danger tape cordon with appropriate signage at access points (scaffolding)
     5 Dispensers (One group of 3 and one group of 2)
    • 13’ exclusion zone (25’ is Plug’s standard and will be utilized)
    o Danger tape cordon with appropriate signage around perimeter

  • 22nd 八月 2026, ALL CLEAR : LIGHTNING STAND DOWN OVER

    GRAY CONSTRUCTION RNO 4-5-6

    LIGHTNING STORM HAS PASSED. ALL WORK CAN RESUME ON ROOF AND EXTERIOR .

  • 15th 八月 2026, Energization-1HL1 and corresponding lightning circuits

    Location: Areas C, D, G, and H
    Zone: Electrical Room
    Time: 2-6pm
    Locations where energizing will take place will be barricaded off.


现场天气预报
当前现场天气

不可用


观测信息来自 - 不可用
时区 - 北美东部标准时间
预测 - 星期一、31 八月

不可用


时区 - 北美东部标准时间
明天 - 星期二, 1 九月

不可用


重要现场文件
刚到这个现场吗?

您知道这个现场的PPE要求吗?

确保您在现场的第一天有正确的安全设备。

查看现场PPE要求

到达现场后尽快开始工作。

在您方便的时候在线完成现场注册,节省您的时间。

开始注册

刚到这个现场吗?

您知道这个现场的PPE要求吗?

确保您在现场的第一天有正确的安全设备。

查看现场PPE要求

刚到这个现场吗?

到达现场后尽快开始工作。

在您方便的时候在线完成现场注册,节省您的时间。

开始注册