  • 29th 8월 2026, Nitrogen Pressure-Testing Plug Power H2 Dispensers Amazon OH 1DC 9am-6pm

    o Testing duration is expected to be 8 hours, starting at 0900 AM
    o All system tubing is 0.38” x 0.065” wall, 0.245 inner diameter.
    o Target test pressure is 7,180 psi
    o Areas being tested and exclusion zones (zones determined using Gray’s safe distance calculator):
     Outdoor hydrogen transfer station (HTS) and field manifold
    • 80’ exclusion zone
    o Danger tape cordon with appropriate signage around perimeter
     Roof area
    • 80’ exclusion zone
    o Danger tape cordon with appropriate signage at access points (scaffolding)
     5 Dispensers (One group of 3 and one group of 2)
    • 13’ exclusion zone (25’ is Plug’s standard and will be utilized)
    o Danger tape cordon with appropriate signage around perimeter

  • 22nd 8월 2026, ALL CLEAR : LIGHTNING STAND DOWN OVER

    GRAY CONSTRUCTION RNO 4-5-6

    LIGHTNING STORM HAS PASSED. ALL WORK CAN RESUME ON ROOF AND EXTERIOR .

  • 15th 8월 2026, Energization-1HL1 and corresponding lightning circuits

    Location: Areas C, D, G, and H
    Zone: Electrical Room
    Time: 2-6pm
    Locations where energizing will take place will be barricaded off.


현장 날씨 예보
현재 현장 날씨

사용할 수 없음


관찰 출처 - 사용할 수 없음
시간대 - 미 동부 표준시
예측 - 월요일, 31 8월

사용할 수 없음


시간대 - 미 동부 표준시
내일 - 화요일, 1 9월

사용할 수 없음


중요한 현장 문서
현장에 처음 오셨나요?

이 현장의 개인 보호 장비(PPE) 요구 사항을 알고 있습니까?

현장 첫날에 올바른 안전 장비를 갖추고 있는지 확인하십시오.

현장 개인 보호 장비 요구 사항 보기

현장에 도착하면 더 빨리 작업을 시작하세요.

편리한 시간에 온라인으로 현장 등록을 완료하고 시간을 절약하세요.

등록 시작

현장에 처음 오셨나요?

이 현장의 개인 보호 장비(PPE) 요구 사항을 알고 있습니까?

현장 첫날에 올바른 안전 장비를 갖추고 있는지 확인하십시오.

현장 개인 보호 장비 요구 사항 보기

현장에 처음 오셨나요?

현장에 도착하면 더 빨리 작업을 시작하세요.

편리한 시간에 온라인으로 현장 등록을 완료하고 시간을 절약하세요.

등록 시작