Amazon 1DC OH - Öffentlicher Projektstandort
-
29th August 2026, Nitrogen Pressure-Testing Plug Power H2 Dispensers Amazon OH 1DC 9am-6pm
o Testing duration is expected to be 8 hours, starting at 0900 AM
o All system tubing is 0.38” x 0.065” wall, 0.245 inner diameter.
o Target test pressure is 7,180 psi
o Areas being tested and exclusion zones (zones determined using Gray’s safe distance calculator):
Outdoor hydrogen transfer station (HTS) and field manifold
• 80’ exclusion zone
o Danger tape cordon with appropriate signage around perimeter
Roof area
• 80’ exclusion zone
o Danger tape cordon with appropriate signage at access points (scaffolding)
5 Dispensers (One group of 3 and one group of 2)
• 13’ exclusion zone (25’ is Plug’s standard and will be utilized)
o Danger tape cordon with appropriate signage around perimeter -
22nd August 2026, ALL CLEAR : LIGHTNING STAND DOWN OVER
GRAY CONSTRUCTION RNO 4-5-6
LIGHTNING STORM HAS PASSED. ALL WORK CAN RESUME ON ROOF AND EXTERIOR . -
15th August 2026, Energization-1HL1 and corresponding lightning circuits
Location: Areas C, D, G, and H
Zone: Electrical Room
Time: 2-6pm
Locations where energizing will take place will be barricaded off.
Aktuelles Wetter am Standort
Nicht verfügbar
Zeitzone - Nordamerikanische Ostküsten-Normalzeit
Vorhersage - Montag, 31 August
Nicht verfügbar
Morgen - Dienstag, 1 September
Nicht verfügbar
Kennen Sie die PPE-Voraussetzungen für diesen Standort?
Stellen Sie sicher, Sie an Ihrem ersten Tag am Standort über die korrekte Sicherheitsausrüstung verfügen.
Fangen Sie früher mit der Arbeit an, wenn Sie vor Ort ankommen.
Füllen Sie Ihre Standortregistrierung online aus und sparen Sie damit Zeit.
Kennen Sie die PPE-Voraussetzungen für diesen Standort?
Stellen Sie sicher, Sie an Ihrem ersten Tag am Standort über die korrekte Sicherheitsausrüstung verfügen.
Fangen Sie früher mit der Arbeit an, wenn Sie vor Ort ankommen.
Füllen Sie Ihre Standortregistrierung online aus und sparen Sie damit Zeit.