Amazon 1DC OH - Sitio de proyecto público
-
29th agosto 2026, Nitrogen Pressure-Testing Plug Power H2 Dispensers Amazon OH 1DC 9am-6pm
o Testing duration is expected to be 8 hours, starting at 0900 AM
o All system tubing is 0.38” x 0.065” wall, 0.245 inner diameter.
o Target test pressure is 7,180 psi
o Areas being tested and exclusion zones (zones determined using Gray’s safe distance calculator):
Outdoor hydrogen transfer station (HTS) and field manifold
• 80’ exclusion zone
o Danger tape cordon with appropriate signage around perimeter
Roof area
• 80’ exclusion zone
o Danger tape cordon with appropriate signage at access points (scaffolding)
5 Dispensers (One group of 3 and one group of 2)
• 13’ exclusion zone (25’ is Plug’s standard and will be utilized)
o Danger tape cordon with appropriate signage around perimeter -
22nd agosto 2026, ALL CLEAR : LIGHTNING STAND DOWN OVER
GRAY CONSTRUCTION RNO 4-5-6
LIGHTNING STORM HAS PASSED. ALL WORK CAN RESUME ON ROOF AND EXTERIOR . -
15th agosto 2026, Energization-1HL1 and corresponding lightning circuits
Location: Areas C, D, G, and H
Zone: Electrical Room
Time: 2-6pm
Locations where energizing will take place will be barricaded off.
Tiempo en Obra actual
No disponible
Zona horaria - hora estándar oriental
Pronóstico - lunes, 31 agosto
No disponible
Mañana - martes, 1 septiembre
No disponible
¿Conoce los requisitos de PPE para esta Obra?
Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.
Empiece a trabajar en cuanto llegue a la obra.
Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.
¿Conoce los requisitos de PPE para esta Obra?
Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.
Empiece a trabajar en cuanto llegue a la obra.
Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.