Amazon 1DC OH - Public Project Site
-
29th August 2026, Nitrogen Pressure-Testing Plug Power H2 Dispensers Amazon OH 1DC 9am-6pm
o Testing duration is expected to be 8 hours, starting at 0900 AM
o All system tubing is 0.38” x 0.065” wall, 0.245 inner diameter.
o Target test pressure is 7,180 psi
o Areas being tested and exclusion zones (zones determined using Gray’s safe distance calculator):
Outdoor hydrogen transfer station (HTS) and field manifold
• 80’ exclusion zone
o Danger tape cordon with appropriate signage around perimeter
Roof area
• 80’ exclusion zone
o Danger tape cordon with appropriate signage at access points (scaffolding)
5 Dispensers (One group of 3 and one group of 2)
• 13’ exclusion zone (25’ is Plug’s standard and will be utilized)
o Danger tape cordon with appropriate signage around perimeter -
22nd August 2026, ALL CLEAR : LIGHTNING STAND DOWN OVER
GRAY CONSTRUCTION RNO 4-5-6
LIGHTNING STORM HAS PASSED. ALL WORK CAN RESUME ON ROOF AND EXTERIOR . -
15th August 2026, Energization-1HL1 and corresponding lightning circuits
Location: Areas C, D, G, and H
Zone: Electrical Room
Time: 2-6pm
Locations where energizing will take place will be barricaded off.
Current Site Weather
Unavailable
Time Zone - Eastern Standard Time
Forecast - Monday, 31 August
Unavailable
Tomorrow - Tuesday, 1 September
Unavailable
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enroll online at your convenience and save yourself time.
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enroll online at your convenience and save yourself time.