Amazon 1DC OH - Lokalizacja publicznego projektu
-
29th sierpnia 2026, Nitrogen Pressure-Testing Plug Power H2 Dispensers Amazon OH 1DC 9am-6pm
o Testing duration is expected to be 8 hours, starting at 0900 AM
o All system tubing is 0.38” x 0.065” wall, 0.245 inner diameter.
o Target test pressure is 7,180 psi
o Areas being tested and exclusion zones (zones determined using Gray’s safe distance calculator):
Outdoor hydrogen transfer station (HTS) and field manifold
• 80’ exclusion zone
o Danger tape cordon with appropriate signage around perimeter
Roof area
• 80’ exclusion zone
o Danger tape cordon with appropriate signage at access points (scaffolding)
5 Dispensers (One group of 3 and one group of 2)
• 13’ exclusion zone (25’ is Plug’s standard and will be utilized)
o Danger tape cordon with appropriate signage around perimeter -
22nd sierpnia 2026, ALL CLEAR : LIGHTNING STAND DOWN OVER
GRAY CONSTRUCTION RNO 4-5-6
LIGHTNING STORM HAS PASSED. ALL WORK CAN RESUME ON ROOF AND EXTERIOR . -
15th sierpnia 2026, Energization-1HL1 and corresponding lightning circuits
Location: Areas C, D, G, and H
Zone: Electrical Room
Time: 2-6pm
Locations where energizing will take place will be barricaded off.
Aktualna pogoda w lokalizacji
Niedostępne
Strefa czasowa - czas wschodnioamerykański standardowy
Prognoza - poniedziałek, 31 sierpnia
Niedostępne
Jutro - wtorek, 1 września
Niedostępne
Czy znasz wymagania dotyczące środków ochrony indywidualnej dla tej lokalizacji?
Upewnij się, że posiadasz właściwy sprzęt BHP na pierwszy dzień w lokalizacji.
Rozpocznij pracę szybciej po przybyciu do lokalizacji
Dokonaj rejestracji online w lokalizacji w wolnej chwili, aby zaoszczędzić czas.
Czy znasz wymagania dotyczące środków ochrony indywidualnej dla tej lokalizacji?
Upewnij się, że posiadasz właściwy sprzęt BHP na pierwszy dzień w lokalizacji.
Rozpocznij pracę szybciej po przybyciu do lokalizacji
Dokonaj rejestracji online w lokalizacji w wolnej chwili, aby zaoszczędzić czas.