Project Mustang
Ngā Pānuirongo Hōu
  • 18th Poutūterangi 2026, RNO4 Fire Protection Systems Going Live

    Team,

    For everyone's awareness there is a final TCO Inspection today with the Fire Marshall at 15:00 for clouds 3 & 4 and power rooms 3 & 4. After said inspection systems will be fully live in a permanent state moving forward.

    Again, this is for clouds 300 400 and the associated power rooms in RNO4 - please treat these as live systems moving forward.

  • 16th Kohitātea 2026, Life Safety: Egress Blocked at Main Office Break Area.

    Please avoid Egress /Exits at the South East Side. Work is taking place outside the Breakroom, Stair Egress, Construction Entrance.

  • 03rd Whiringa ā-rangi 2025, Stop work due to high winds

    All roof work, outdoor elevated work, and crane activities must stop due to high wind speeds.

Matapae Huarere Paemahi
Huarere Paemahi Onāianei

Korewātea


Kitenga i pūtake mai i - Korewātea
Rohe Wā - Wā Arowhānui Maunga
Matapae - Rāpare, 2 Paengawhāwhā

Korewātea


Rohe Wā - Wā Arowhānui Maunga
Āpōpō - Rāmere, 3 Paengawhāwhā

Korewātea


Ngā Tuhinga Paemahi Hira
Tauhōu ki te Paemahi?

E mōhio ana rānei koe ki ngā Whakaritenga PPE mō tēnei paemahi?

Āta tiaki kei a koe ngā taputapu haumarutanga tika mō tō rā tuatahi i te paemahi.

Tiro Whakaritenga PPE Paemahi

Tīmata wawe ake ina tae koe ki te paemahi.

Whakaotia tuihonotia tō rēhitatanga paemahi ina pai koe hei penapena tāima.

Tīmataria te Rēhitatanga

Tauhōu ki te Paemahi?

E mōhio ana rānei koe ki ngā Whakaritenga PPE mō tēnei paemahi?

Āta tiaki kei a koe ngā taputapu haumarutanga tika mō tō rā tuatahi i te paemahi.

Tiro Whakaritenga PPE Paemahi

Tauhōu ki te Paemahi?

Tīmata wawe ake ina tae koe ki te paemahi.

Whakaotia tuihonotia tō rēhitatanga paemahi ina pai koe hei penapena tāima.

Tīmataria te Rēhitatanga