Project Mustang
Nedávné bulletiny
  • 18th března 2026, RNO4 Fire Protection Systems Going Live

    Team,

    For everyone's awareness there is a final TCO Inspection today with the Fire Marshall at 15:00 for clouds 3 & 4 and power rooms 3 & 4. After said inspection systems will be fully live in a permanent state moving forward.

    Again, this is for clouds 300 400 and the associated power rooms in RNO4 - please treat these as live systems moving forward.

  • 16th ledna 2026, Life Safety: Egress Blocked at Main Office Break Area.

    Please avoid Egress /Exits at the South East Side. Work is taking place outside the Breakroom, Stair Egress, Construction Entrance.

  • 03rd listopadu 2025, Stop work due to high winds

    All roof work, outdoor elevated work, and crane activities must stop due to high wind speeds.

Předpověď počasí pro stavbu
Aktuální počasí na pracovišti

Nedostupné


Pozorování vycházející z - Nedostupné
Časové pásmo - severoamerický horský standardní čas
Předpověď – čtvrtek, 2 dubna

Nedostupné


Časové pásmo - severoamerický horský standardní čas
Zítra - pátek, 3 dubna

Nedostupné


Důležité dokumenty pracoviště
Novinka na pracovišti?

Znáte požadavky na OOPP pro toto pracoviště?

Ujistěte se, zda máte pro první den na pracovišti správné bezpečnostní vybavení.

Zobrazit požadavky na OOPP ke stavbě

Po příjezdu na místo můžete začít pracovat dříve.

Jakmile budete moci, dokončete registraci do pracoviště online, a ušetřete si tak čas.

Začít registraci

Novinka na pracovišti?

Znáte požadavky na OOPP pro toto pracoviště?

Ujistěte se, zda máte pro první den na pracovišti správné bezpečnostní vybavení.

Zobrazit požadavky na OOPP ke stavbě

Novinka na pracovišti?

Po příjezdu na místo můžete začít pracovat dříve.

Jakmile budete moci, dokončete registraci do pracoviště online, a ušetřete si tak čas.

Začít registraci