Son Bültenler
  • 30th Eylül 2026, BUILDING RNO 4 test mode

    BUILDING RNO 4 HAS BEEN PLACED ON TEST
    START- 5:30 AM
    END- 5:00 PM

  • 22nd Ağustos 2026, ALL CLEAR : LIGHTNING STAND DOWN OVER

    GRAY CONSTRUCTION RNO 4-5-6

    LIGHTNING STORM HAS PASSED. ALL WORK CAN RESUME ON ROOF AND EXTERIOR .

  • 19th Ağustos 2026, RNO6 Transformer Crane Pick 8/19/2026

    All,

    Today, 8/19/2026, we will be having a crane pick for the transformers on the gen pad just south of the loading dock. I have attached the exclusion zone to this bulletin. During this time only authorized personnel will be allowed in this area. If anyone has any questions please contact Gray.

    Ekler :
    Screenshot 2026-08-19 071003.png
Saha Hava Durumu Tahmini
Geçerli Saha Hava Durumu

Kullanılamaz


Gözlem kaynağı - Kullanılamaz
Zaman Dilimi - Kuzey Amerika Dağ Standart Saati
Tahmin - Cumartesi, 10 Ekim

Kullanılamaz


Zaman Dilimi - Kuzey Amerika Dağ Standart Saati
Yarın - Pazar, 11 Ekim

Kullanılamaz


Önemli Saha Belgeleri
Sahada Yeni misiniz?

Bu sahanın KKD Gereksinimlerini biliyor musunuz?

Sahadaki ilk gününüzde doğru güvenlik ekipmanlarına sahip olduğunuzdan emin olun.

Saha KKD Gereksinimlerini Görüntüle

Sahaya geldiğinizde kısa süre içinde çalışmaya başlamak için hazırlanın.

Saha kaydınızı çevrimiçi tamamlayın ve zamandan kazanın.

Kayda Başla

Sahada Yeni misiniz?

Bu sahanın KKD Gereksinimlerini biliyor musunuz?

Sahadaki ilk gününüzde doğru güvenlik ekipmanlarına sahip olduğunuzdan emin olun.

Saha KKD Gereksinimlerini Görüntüle

Sahada Yeni misiniz?

Sahaya geldiğinizde kısa süre içinde çalışmaya başlamak için hazırlanın.

Saha kaydınızı çevrimiçi tamamlayın ve zamandan kazanın.

Kayda Başla