Switch - RNO 6 - Offentlig projektarbejdsplads
-
30th september 2026, BUILDING RNO 4 test mode
BUILDING RNO 4 HAS BEEN PLACED ON TEST
START- 5:30 AM
END- 5:00 PM -
22nd august 2026, ALL CLEAR : LIGHTNING STAND DOWN OVER
GRAY CONSTRUCTION RNO 4-5-6
LIGHTNING STORM HAS PASSED. ALL WORK CAN RESUME ON ROOF AND EXTERIOR . -
19th august 2026, RNO6 Transformer Crane Pick 8/19/2026
All,
Vedhæftede filer :
Today, 8/19/2026, we will be having a crane pick for the transformers on the gen pad just south of the loading dock. I have attached the exclusion zone to this bulletin. During this time only authorized personnel will be allowed in this area. If anyone has any questions please contact Gray.
Screenshot 2026-08-19 071003.png
Aktuelt vejr på stedet
Utilgængelig
Tidszone - Mountain-normaltid
Prognose - lørdag, 10 oktober
Utilgængelig
Imorgen - søndag, 11 oktober
Utilgængelig
Kender du kravene for personlige værnemidler til dette sted?
Sørg for, at du har det korrekte sikkerhedsudstyr til din første dag på arbejdspladsen.
Kom hurtigere i gang med arbejdet, når du ankommer til stedet.
Afslut din webstedsregistrering online, når det passer dig, og spar tid.
Kender du kravene for personlige værnemidler til dette sted?
Sørg for, at du har det korrekte sikkerhedsudstyr til din første dag på arbejdspladsen.
Kom hurtigere i gang med arbejdet, når du ankommer til stedet.
Afslut din webstedsregistrering online, når det passer dig, og spar tid.