Switch - RNO 6 - Site du projet public
-
19th janvier 2026, Cosco Testing Power rooms 400’s/300’s
Testing in power rooms 400’s/300’s will be commencing at 9am on 1/19 until 1/21 at 40PSI.
Be aware that NO overhead work is allowed, only ground work. Also be aware that you must be 20ft away from any fire protection piping if you enter in these power rooms. -
19th novembre 2025, Roof Work Suspension
Hello Team,
This is to inform all trade partners that all roof work and rooftop activity is suspended effective immediately. Ice is currently present on the roof surface, creating unsafe working conditions.
No work may proceed on the roof until the ice has fully melted or until further notice is issued.
Thank you
for your cooperation and commitment to safety. -
03rd novembre 2025, Stop work due to high winds
All roof work, outdoor elevated work, and crane activities must stop due to high wind speeds.
Météo sur le site actuel
Indisponible
Fuseau horaire - heure normale des Rocheuses
Prévision - mercredi, 11 février
Indisponible
Demain - jeudi, 12 février
Indisponible
Connaissez-vous les exigences en matière de PPE pour ce site ?
Assurez-vous que vous avez l'équipement de sécurité approprié lors de votre premier jour sur le site.
Commencez à travailler plus tôt dès votre arrivée sur le site.
Complétez votre inscription du site en ligne à votre convenance et gagnez du temps par la même occasion.
Connaissez-vous les exigences en matière de PPE pour ce site ?
Assurez-vous que vous avez l'équipement de sécurité approprié lors de votre premier jour sur le site.
Commencez à travailler plus tôt dès votre arrivée sur le site.
Complétez votre inscription du site en ligne à votre convenance et gagnez du temps par la même occasion.