Switch - RNO 6 - Openbare Project Locatie
-
19th januari 2026, Cosco Testing Power rooms 400’s/300’s
Testing in power rooms 400’s/300’s will be commencing at 9am on 1/19 until 1/21 at 40PSI.
Be aware that NO overhead work is allowed, only ground work. Also be aware that you must be 20ft away from any fire protection piping if you enter in these power rooms. -
19th november 2025, Roof Work Suspension
Hello Team,
This is to inform all trade partners that all roof work and rooftop activity is suspended effective immediately. Ice is currently present on the roof surface, creating unsafe working conditions.
No work may proceed on the roof until the ice has fully melted or until further notice is issued.
Thank you
for your cooperation and commitment to safety. -
03rd november 2025, Stop work due to high winds
All roof work, outdoor elevated work, and crane activities must stop due to high wind speeds.
Huidige weersomstandigheden op locatie
Niet beschikbaar
Tijdzone - Mountain-standaardtijd
Weerbericht - woensdag, 11 februari
Niet beschikbaar
Morgen - donderdag, 12 februari
Niet beschikbaar
Weet u wat de PBM-vereisten voor deze locatie zijn?
Zorg dat u voor uw eerste dag op de locatie de juiste veiligheidsapparatuur hebt.
Begin sneller te werken zodra u op de locatie aankomt.
Voltooi uw locatieregistratie eenvoudig online en bespaar zo kostbare tijd.
Weet u wat de PBM-vereisten voor deze locatie zijn?
Zorg dat u voor uw eerste dag op de locatie de juiste veiligheidsapparatuur hebt.
Begin sneller te werken zodra u op de locatie aankomt.
Voltooi uw locatieregistratie eenvoudig online en bespaar zo kostbare tijd.