19th gennaio 2026, Cosco Testing Power rooms 400’s/300’s
Testing in power rooms 400’s/300’s will be commencing at 9am on 1/19 until 1/21 at 40PSI.
Be aware that NO overhead work is allowed, only ground work. Also be aware that you must be 20ft away from any fire protection piping if you enter in these power rooms. -
19th novembre 2025, Roof Work Suspension
Hello Team,
This is to inform all trade partners that all roof work and rooftop activity is suspended effective immediately. Ice is currently present on the roof surface, creating unsafe working conditions.
No work may proceed on the roof until the ice has fully melted or until further notice is issued.
Thank you
for your cooperation and commitment to safety. -
03rd novembre 2025, Stop work due to high winds
All roof work, outdoor elevated work, and crane activities must stop due to high wind speeds.
Meteo attuale del cantiere
Non disponibile
Fuso orario - Ora standard Montagne Rocciose USA
Previsioni - mercoledì, 11 febbraio
Non disponibile
Domani - giovedì, 12 febbraio
Non disponibile
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.