08th September 2025, 24-48 hour notice of energization
Team
there will be a first time energization of the 2100 MODs 01s & 03s on Tuesday 09.09.25 starting at 8:30 am in the westside Gallery on the second level. The Gallery will be closed off till Approximately 12pm. Please adhere to all Barricades, CAZs, and signage, as only qualified persons will be allowed in the gallery. -
05th September 2025, Cosco RNO 5 Fire Suppression Testing
Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.
Attachments :
Power room 4 5 6 .pdf
Aboveground Test Cert copy .pdf
IMG_0383.jpg
Switch5 system 5&6.pdf
System 14.pdf
-
03rd September 2025, RNO4 Area L Power Rooms Pressure Test 9/3/25
All - Please see below details for ACCO Pressure test to take place in RNO4 tomorrow 9/3/25.
Attachments :
Location: RNO4 Sector L Power Rooms (Vaults 7 & 8)
System: 10" Chilled Water Piping
Pressure: 150 PSI Hydrostatic
Test Duration: 3 hours (1 hour fill 2 hours test)
Exclusion zone will only prohibit work taking place above 10' from finished floor.
Exclusion starts: 9/3/2025 3:00PM
Exclusion expected end: 9/3/25 6:00PM
Sector L Test #L1 10 inch Markup Power Rooms.pdf
Current Site Weather
Unavailable
Time Zone - Eastern Standard Time
Forecast - Sunday, 14 September
Unavailable
Tomorrow - Monday, 15 September
Unavailable
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Complete your site registration online at your convenience and save yourself time.
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Complete your site registration online at your convenience and save yourself time.