QTS - NAL2 DC2 - Öffentlicher Projektstandort
-
01st Juli 2025, 24-48 hour energization notice
All
We will be energizing HSE-SWR (house switch gear) on 07.02.25 at 11am in DC1. All unauthorized personnel must vacate the area. Please pay attention to all signage, barricades, and CAZs -
01st Juli 2025, 48hour energization notice for Gens A21-R21
We will be energizing shore power at GENs A21-R21 in Gen yard of DC1 on 07.03.25 at 9-11:30am. All unauthorized work in or near the equipment is to be stopped until energization is complete. Please be aware of and respect all barricades, CAZs and signage blocking off area.
-
19th Juni 2025, 48 hour energization notice
All
we will be energizing shore power in Gens G11 & R11 in gen yard of DC1. please adhere to all signage and barricades. Only authorized personnel to be allowed into equipment. NF
Aktuelles Wetter am Standort
Nicht verfügbar
Zeitzone - Nordamerikanische Ostküsten-Normalzeit
Vorhersage - Mittwoch, 2 Juli
Nicht verfügbar
Morgen - Donnerstag, 3 Juli
Nicht verfügbar
Kennen Sie die PPE-Voraussetzungen für diesen Standort?
Stellen Sie sicher, Sie an Ihrem ersten Tag am Standort über die korrekte Sicherheitsausrüstung verfügen.
Fangen Sie früher mit der Arbeit an, wenn Sie vor Ort ankommen.
Füllen Sie Ihre Standortregistrierung online aus und sparen Sie damit Zeit.
Kennen Sie die PPE-Voraussetzungen für diesen Standort?
Stellen Sie sicher, Sie an Ihrem ersten Tag am Standort über die korrekte Sicherheitsausrüstung verfügen.
Fangen Sie früher mit der Arbeit an, wenn Sie vor Ort ankommen.
Füllen Sie Ihre Standortregistrierung online aus und sparen Sie damit Zeit.