08th October 2025, Energization notice
Team
We will be energizing MVG 04 at the very south end of DC2 at 6:30am 10.08.25. the south end of the building will be off limits to all unauthorized personnel. please pay attention to all signage and barricades -
07th October 2025, DC2 Outage
All,
Between 1-2 PM (EST), there will be a power outage due to generator maintenance. Apologies for the inconvenience. -
01st October 2025, Site Entrance Change
To All Site Vendors and Trade Partners,
Please be advised that effective tomorrow, Gray will be relocating the primary site entrance to the Southeast end of the project site.
This change may impact transportation logistics, especially for individuals utilizing the bus system from the remote lots. Although additional buses/drivers are being added, traffic patterns and the uncertainty of this change may cause delays during this transition.
We strongly encourage all personnel to plan accordingly and arrive early to ensure they are at their designated work areas on time.
This temporary condition will remain in effect until next week, when the secondary entrance from Babbitt Road into the remote lot is scheduled to open.
We appreciate your cooperation and understanding as we work to improve site access and maintain safety for everyone.
If you have any questions, please contact the Gray field office.
Current Site Weather
Unavailable
Time Zone - Eastern Standard Time
Forecast - Wednesday, 8 October
Unavailable
Tomorrow - Thursday, 9 October
Unavailable
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enroll online at your convenience and save yourself time.
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enroll online at your convenience and save yourself time.