15th Mahuru 2025, SITE SHUT DOWN 4PM 9/17
ALL INTERIOR WORK WILL BE SHUT DOWN AT 4PM ON 9/17 FOR AIR TESTING ON THE FIRE STANDPIPE SYSTEM IN THE BUILDING. PLEASE PLAN ALL WORK ACCORDINGLY.
-
15th Mahuru 2025, RNO4 Cloud 600 ROOF Piping Testing
Morning all,
This email is to notify all trade partners that there will be a test conducted today on the RNO4 Roof in cloud 600.
Location RNO4 cloud 6 ROOF
System: Chilled water
Pressure: 150 PSI
Duration: 2 hours
Start time: 9/15 1500
End Time: 9/15 1730
Questions? Have your FOREMAN contact Alex Pifer with Gray,
Appreciate your cooperation.
Thank you
-
05th Mahuru 2025, Cosco RNO 5 Fire Suppression Testing
Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.
Ngā Āpitihanga :
Power room 4 5 6 .pdf
Aboveground Test Cert copy .pdf
IMG_0383.jpg
Switch5 system 5&6.pdf
System 14.pdf
Huarere Paemahi Onāianei
Korewātea
Rohe Wā - Wā Arowhānui Maunga
Matapae - Rāapa, 8 Whiringa ā-nuku
Korewātea
Āpōpō - Rāpare, 9 Whiringa ā-nuku
Korewātea
E mōhio ana rānei koe ki ngā Whakaritenga PPE mō tēnei paemahi?
Āta tiaki kei a koe ngā taputapu haumarutanga tika mō tō rā tuatahi i te paemahi.
Tīmata wawe ake ina tae koe ki te paemahi.
Whakaotia tuihonotia tō rēhitatanga paemahi ina pai koe hei penapena tāima.
E mōhio ana rānei koe ki ngā Whakaritenga PPE mō tēnei paemahi?
Āta tiaki kei a koe ngā taputapu haumarutanga tika mō tō rā tuatahi i te paemahi.
Tīmata wawe ake ina tae koe ki te paemahi.
Whakaotia tuihonotia tō rēhitatanga paemahi ina pai koe hei penapena tāima.