15th settembre 2025, SITE SHUT DOWN 4PM 9/17
ALL INTERIOR WORK WILL BE SHUT DOWN AT 4PM ON 9/17 FOR AIR TESTING ON THE FIRE STANDPIPE SYSTEM IN THE BUILDING. PLEASE PLAN ALL WORK ACCORDINGLY.
-
15th settembre 2025, RNO4 Cloud 600 ROOF Piping Testing
Morning all,
This email is to notify all trade partners that there will be a test conducted today on the RNO4 Roof in cloud 600.
Location RNO4 cloud 6 ROOF
System: Chilled water
Pressure: 150 PSI
Duration: 2 hours
Start time: 9/15 1500
End Time: 9/15 1730
Questions? Have your FOREMAN contact Alex Pifer with Gray,
Appreciate your cooperation.
Thank you
-
05th settembre 2025, Cosco RNO 5 Fire Suppression Testing
Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.
Allegati :
Power room 4 5 6 .pdf
Aboveground Test Cert copy .pdf
IMG_0383.jpg
Switch5 system 5&6.pdf
System 14.pdf
Meteo attuale del cantiere
Non disponibile
Fuso orario - Ora standard Montagne Rocciose USA
Previsioni - mercoledì, 8 ottobre
Non disponibile
Domani - giovedì, 9 ottobre
Non disponibile
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.