Nathan Trotter & Company - Project Oz - 공공 프로젝트 현장
-
25th 4월 2025, 48 hour MVG 01/04 Energization
All
This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project. -
25th 4월 2025, 48 hour Energization notice
All
This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project. -
14th 4월 2025, PreTesting
There will be Pretesting for Strobes and Lights for Building 109. CSI is heading this up.
현재 현장 날씨
사용할 수 없음
시간대 - 미 동부 표준시
예측 - 토요일, 26 4월
사용할 수 없음
내일 - 일요일, 27 4월
사용할 수 없음