Nathan Trotter & Company - Project Oz
최근 게시판
  • 25th 4월 2025, 48 hour MVG 01/04 Energization

    All

    This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project.

  • 25th 4월 2025, 48 hour Energization notice

    All

    This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project.

  • 14th 4월 2025, PreTesting

    There will be Pretesting for Strobes and Lights for Building 109. CSI is heading this up.

현장 날씨 예보
현재 현장 날씨

사용할 수 없음


관찰 출처 - 사용할 수 없음
시간대 - 미 동부 표준시
예측 - 토요일, 26 4월

사용할 수 없음


시간대 - 미 동부 표준시
내일 - 일요일, 27 4월

사용할 수 없음


중요한 현장 문서
현장에 처음 오셨나요?

이 현장의 개인 보호 장비(PPE) 요구 사항을 알고 있습니까?

현장 첫날에 올바른 안전 장비를 갖추고 있는지 확인하십시오.

현장 개인 보호 장비 요구 사항 보기

현장에 도착하면 더 빨리 작업을 시작하세요.

편리한 시간에 온라인으로 현장 등록을 완료하고 시간을 절약하세요.

등록 시작

현장에 처음 오셨나요?

이 현장의 개인 보호 장비(PPE) 요구 사항을 알고 있습니까?

현장 첫날에 올바른 안전 장비를 갖추고 있는지 확인하십시오.

현장 개인 보호 장비 요구 사항 보기

현장에 처음 오셨나요?

현장에 도착하면 더 빨리 작업을 시작하세요.

편리한 시간에 온라인으로 현장 등록을 완료하고 시간을 절약하세요.

등록 시작