25th abril 2025, 48 hour MVG 01/04 Energization
All
This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project. -
25th abril 2025, 48 hour Energization notice
All
This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project. -
14th abril 2025, PreTesting
There will be Pretesting for Strobes and Lights for Building 109. CSI is heading this up.
Tiempo en Obra actual
No disponible
Zona horaria - hora estándar oriental
Pronóstico - sábado, 26 abril
No disponible
Mañana - domingo, 27 abril
No disponible
¿Conoce los requisitos de PPE para esta Obra?
Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.
Empiece a trabajar en cuanto llegue a la obra.
Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.
¿Conoce los requisitos de PPE para esta Obra?
Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.
Empiece a trabajar en cuanto llegue a la obra.
Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.