Gray AES - JR Simplot - 公共プロジェクト現場
-
15th 9月 2025, SITE SHUT DOWN 4PM 9/17
ALL INTERIOR WORK WILL BE SHUT DOWN AT 4PM ON 9/17 FOR AIR TESTING ON THE FIRE STANDPIPE SYSTEM IN THE BUILDING. PLEASE PLAN ALL WORK ACCORDINGLY.
-
15th 9月 2025, RNO4 Cloud 600 ROOF Piping Testing
Morning all,
This email is to notify all trade partners that there will be a test conducted today on the RNO4 Roof in cloud 600.
Location RNO4 cloud 6 ROOF
System: Chilled water
Pressure: 150 PSI
Duration: 2 hours
Start time: 9/15 1500
End Time: 9/15 1730
Questions? Have your FOREMAN contact Alex Pifer with Gray,
Appreciate your cooperation.
Thank you
-
05th 9月 2025, Cosco RNO 5 Fire Suppression Testing
Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.
添付ファイル :
Power room 4 5 6 .pdf
Aboveground Test Cert copy .pdf
IMG_0383.jpg
Switch5 system 5&6.pdf
System 14.pdf
現在の現場の天気
最終更新日時: 21:06
温度: 13C
風速: 15KMH
最大風速: 22KMH @15:06
最低気温: 5C @4:06
最高気温: 22C @16:03
突風: 16KMH
最大突風: 30KMH @14:06
観察場所 - Pocatello, ID
タイムゾーン - アメリカ山地標準時
予測 - 水曜日, 8 10月
sky is clear
分: 7C マックス: 22C
予測場所 - Pocatello, ID
タイムゾーン - アメリカ山地標準時
明日 - 木曜日, 9 10月
sky is clear
分: 10C マックス: 25C