Costco Fleet Restroom Sugar Land - Lokalizacja publicznego projektu
-
15th września 2025, SITE SHUT DOWN 4PM 9/17
ALL INTERIOR WORK WILL BE SHUT DOWN AT 4PM ON 9/17 FOR AIR TESTING ON THE FIRE STANDPIPE SYSTEM IN THE BUILDING. PLEASE PLAN ALL WORK ACCORDINGLY.
-
15th września 2025, RNO4 Cloud 600 ROOF Piping Testing
Morning all,
This email is to notify all trade partners that there will be a test conducted today on the RNO4 Roof in cloud 600.
Location RNO4 cloud 6 ROOF
System: Chilled water
Pressure: 150 PSI
Duration: 2 hours
Start time: 9/15 1500
End Time: 9/15 1730
Questions? Have your FOREMAN contact Alex Pifer with Gray,
Appreciate your cooperation.
Thank you
-
05th września 2025, Cosco RNO 5 Fire Suppression Testing
Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.
Załączniki :
Power room 4 5 6 .pdf
Aboveground Test Cert copy .pdf
IMG_0383.jpg
Switch5 system 5&6.pdf
System 14.pdf
Aktualna pogoda w lokalizacji
Niedostępne
Strefa czasowa - czas środkowoamerykański standardowy
Prognoza - środa, 8 października
Niedostępne
Jutro - czwartek, 9 października
Niedostępne
Czy znasz wymagania dotyczące środków ochrony indywidualnej dla tej lokalizacji?
Upewnij się, że posiadasz właściwy sprzęt BHP na pierwszy dzień w lokalizacji.
Rozpocznij pracę szybciej po przybyciu do lokalizacji
Dokonaj rejestracji online w lokalizacji w wolnej chwili, aby zaoszczędzić czas.
Czy znasz wymagania dotyczące środków ochrony indywidualnej dla tej lokalizacji?
Upewnij się, że posiadasz właściwy sprzęt BHP na pierwszy dzień w lokalizacji.
Rozpocznij pracę szybciej po przybyciu do lokalizacji
Dokonaj rejestracji online w lokalizacji w wolnej chwili, aby zaoszczędzić czas.