15th septembre 2025, SITE SHUT DOWN 4PM 9/17
ALL INTERIOR WORK WILL BE SHUT DOWN AT 4PM ON 9/17 FOR AIR TESTING ON THE FIRE STANDPIPE SYSTEM IN THE BUILDING. PLEASE PLAN ALL WORK ACCORDINGLY.
-
15th septembre 2025, RNO4 Cloud 600 ROOF Piping Testing
Morning all,
This email is to notify all trade partners that there will be a test conducted today on the RNO4 Roof in cloud 600.
Location RNO4 cloud 6 ROOF
System: Chilled water
Pressure: 150 PSI
Duration: 2 hours
Start time: 9/15 1500
End Time: 9/15 1730
Questions? Have your FOREMAN contact Alex Pifer with Gray,
Appreciate your cooperation.
Thank you
-
05th septembre 2025, Cosco RNO 5 Fire Suppression Testing
Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.
Pièces jointes :
Power room 4 5 6 .pdf
Aboveground Test Cert copy .pdf
IMG_0383.jpg
Switch5 system 5&6.pdf
System 14.pdf
Météo sur le site actuel
Indisponible
Fuseau horaire - heure normale du Centre
Prévision - mercredi, 8 octobre
Indisponible
Demain - jeudi, 9 octobre
Indisponible
Connaissez-vous les exigences en matière de PPE pour ce site ?
Assurez-vous que vous avez l'équipement de sécurité approprié lors de votre premier jour sur le site.
Commencez à travailler plus tôt dès votre arrivée sur le site.
Complétez votre inscription du site en ligne à votre convenance et gagnez du temps par la même occasion.
Connaissez-vous les exigences en matière de PPE pour ce site ?
Assurez-vous que vous avez l'équipement de sécurité approprié lors de votre premier jour sur le site.
Commencez à travailler plus tôt dès votre arrivée sur le site.
Complétez votre inscription du site en ligne à votre convenance et gagnez du temps par la même occasion.