Recent Bulletins
  • 15th September 2025, SITE SHUT DOWN 4PM 9/17

    ALL INTERIOR WORK WILL BE SHUT DOWN AT 4PM ON 9/17 FOR AIR TESTING ON THE FIRE STANDPIPE SYSTEM IN THE BUILDING. PLEASE PLAN ALL WORK ACCORDINGLY.

  • 15th September 2025, RNO4 Cloud 600 ROOF Piping Testing

    Morning all,

    This email is to notify all trade partners that there will be a test conducted today on the RNO4 Roof in cloud 600.

    Location RNO4 cloud 6 ROOF
    System: Chilled water
    Pressure: 150 PSI
    Duration: 2 hours

    Start time: 9/15 1500
    End Time: 9/15 1730

    Questions? Have your FOREMAN contact Alex Pifer with Gray,
    Appreciate your cooperation.

    Thank you

  • 05th September 2025, Cosco RNO 5 Fire Suppression Testing

    Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.

    Attachments :
    Power room 4 5 6 .pdf
    Aboveground Test Cert copy .pdf
    IMG_0383.jpg
    Switch5 system 5&6.pdf
    System 14.pdf
Site Weather Forecast
Current Site Weather

Unavailable


Observation sourced from - Unavailable
Time Zone - Eastern Standard Time
Forecast - Wednesday, 8 October

Unavailable


Time Zone - Eastern Standard Time
Tomorrow - Thursday, 9 October

Unavailable


Important Site Documents
New to Site?

Do you know the PPE Requirements for this site?

Ensure you have the correct safety equipment for your first day at the site.

View Site PPE Requirements

Get started working sooner when you arrive on site.

Enroll online at your convenience and save yourself time.

Begin Enrollment

New to Site?

Do you know the PPE Requirements for this site?

Ensure you have the correct safety equipment for your first day at the site.

View Site PPE Requirements

New to Site?

Get started working sooner when you arrive on site.

Enroll online at your convenience and save yourself time.

Begin Enrollment