QTS NAL3 - Site - सार्वजनिक प्रोजेक्ट साइट
-
25th अप्रैल 2025, 48 hour MVG 01/04 Energization
All
This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project. -
25th अप्रैल 2025, 48 hour Energization notice
All
This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project. -
14th अप्रैल 2025, PreTesting
There will be Pretesting for Strobes and Lights for Building 109. CSI is heading this up.
साइट का मौजूदा मौसम
उपलब्ध नहीं है
समय क्षेत्र - उत्तरी अमेरिकी पूर्वी मानक समय
पूर्वानुमान - शनिवार, 26 अप्रैल
उपलब्ध नहीं है
कल - रविवार, 27 अप्रैल
उपलब्ध नहीं है
क्या आप इस साइट के लिए आवश्यक PPE के बारे में जानते हैं?
सुनिश्चित करें कि आपके पास साइट पर पहले दिन के लिए सही सुरक्षा इक्विपमेंट हैं।
जब आप साइट पर पहुंचें, तो जल्द से जल्द काम करना शुरू कर दें।
अपनी सुविधा के अनुसार अपना साइट रजिस्ट्रेशन ऑनलाइन पूरा करें और अपना समय बचाएँ।
क्या आप इस साइट के लिए आवश्यक PPE के बारे में जानते हैं?
सुनिश्चित करें कि आपके पास साइट पर पहले दिन के लिए सही सुरक्षा इक्विपमेंट हैं।
जब आप साइट पर पहुंचें, तो जल्द से जल्द काम करना शुरू कर दें।
अपनी सुविधा के अनुसार अपना साइट रजिस्ट्रेशन ऑनलाइन पूरा करें और अपना समय बचाएँ।