03rd listopada 2025, Stop work due to high winds
All roof work, outdoor elevated work, and crane activities must stop due to high wind speeds.
-
22nd października 2025, RNO4 VCU 39 pneumatic testing on 10/23/25
Safety team,
Please see below outlined bulletin for testing tomorrow and send to trades via bulletin.
Location: RNO4 admin area
System: Copper Refrigeration Lines
Pressure: 600 psi
Duration: 24 hours
Exclusion zone starts: 7:00 AM 10/23/25
Exclusion zone expected end: 8:00 AM 10/24/25
Acco Plumbing will be performing a pneumatic test in area 39, Test pressure is 600 psi for 24 hours hold time.
Please avoid these test area and barricades. Exclusion zones are barricaded and not to be crossed.
-
21st października 2025, Generator Maintenance
Generator for temp power will go down starting on the eastside first and then moving to the westside these shut down will only affect the building 30 minutes at a time.
FYI: This will happen every other week.
Aktualna pogoda w lokalizacji
Niedostępne
Strefa czasowa - czas wschodnioamerykański standardowy
Prognoza - niedziela, 14 grudnia
Niedostępne
Jutro - poniedziałek, 15 grudnia
Niedostępne
Czy znasz wymagania dotyczące środków ochrony indywidualnej dla tej lokalizacji?
Upewnij się, że posiadasz właściwy sprzęt BHP na pierwszy dzień w lokalizacji.
Rozpocznij pracę szybciej po przybyciu do lokalizacji
Dokonaj rejestracji online w lokalizacji w wolnej chwili, aby zaoszczędzić czas.
Czy znasz wymagania dotyczące środków ochrony indywidualnej dla tej lokalizacji?
Upewnij się, że posiadasz właściwy sprzęt BHP na pierwszy dzień w lokalizacji.
Rozpocznij pracę szybciej po przybyciu do lokalizacji
Dokonaj rejestracji online w lokalizacji w wolnej chwili, aby zaoszczędzić czas.