Owens Corning – Project Thunder
最近のニュースレター
  • 05th 9月 2025, Cosco RNO 5 Fire Suppression Testing

    Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.

    添付ファイル :
    Power room 4 5 6 .pdf
    Aboveground Test Cert copy .pdf
    IMG_0383.jpg
    Switch5 system 5&6.pdf
    System 14.pdf
  • 03rd 9月 2025, RNO4 Area L Power Rooms Pressure Test 9/3/25

    All - Please see below details for ACCO Pressure test to take place in RNO4 tomorrow 9/3/25.

    Location: RNO4 Sector L Power Rooms (Vaults 7 & 8)

    System: 10" Chilled Water Piping
    Pressure: 150 PSI Hydrostatic
    Test Duration: 3 hours (1 hour fill 2 hours test)

    Exclusion zone will only prohibit work taking place above 10' from finished floor.
    Exclusion starts: 9/3/2025 3:00PM
    Exclusion expected end: 9/3/25 6:00PM

    添付ファイル :
    Sector L Test #L1 10 inch Markup Power Rooms.pdf
  • 02nd 9月 2025, REVISED RNO4 3pm Pressure Testing Power Room 605

    Pressure testing will be at 3:00 PM in Power Room 605

現場天気予報
現在の現場の天気

利用できません


観察元 - 利用できません
タイムゾーン - アメリカ中部標準時
予測 - 日曜日, 14 9月

利用できません


タイムゾーン - アメリカ中部標準時
明日 - 月曜日, 15 9月

利用できません


重要な現場書類
現場に初めてですか?

この現場のPPE要件を知っていますか?

現場での初日に備えて、適切な安全装備を確保してください。

現場のPPE要件を表示

現場に到着したら、すぐに作業を開始できます。

ご都合の良い時にオンラインで現場登録を完了し、時間を節約してください。

登録を開始

現場に初めてですか?

この現場のPPE要件を知っていますか?

現場での初日に備えて、適切な安全装備を確保してください。

現場のPPE要件を表示

現場に初めてですか?

現場に到着したら、すぐに作業を開始できます。

ご都合の良い時にオンラインで現場登録を完了し、時間を節約してください。

登録を開始