25th aprilie 2025, 48 hour MVG 01/04 Energization
All
This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project. -
25th aprilie 2025, 48 hour Energization notice
All
This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project. -
14th aprilie 2025, PreTesting
There will be Pretesting for Strobes and Lights for Building 109. CSI is heading this up.
Condiții meteo curente la șantier
Indisponibil
Fus orar - Ora standard orientală nord-americană
Prognoză - sâmbătă, 26 aprilie
Indisponibil
Mâine - duminică, 27 aprilie
Indisponibil
Cunoașteți cerințele EIP pentru acest șantier?
Asigurați-vă că aveți echipamentul de siguranță corect pentru prima zi la locație.
Începeți să lucrați mai devreme atunci când ajungeți în locație.
Finalizați înregistrarea la șantier online când doriți și economisiți timp.
Cunoașteți cerințele EIP pentru acest șantier?
Asigurați-vă că aveți echipamentul de siguranță corect pentru prima zi la locație.
Începeți să lucrați mai devreme atunci când ajungeți în locație.
Finalizați înregistrarea la șantier online când doriți și economisiți timp.