22nd August 2026, ALL CLEAR : LIGHTNING STAND DOWN OVER
GRAY CONSTRUCTION RNO 4-5-6
LIGHTNING STORM HAS PASSED. ALL WORK CAN RESUME ON ROOF AND EXTERIOR . -
03rd August 2026, Building RNO4 Test Mode (full System)
Building RNO4 has been placed into test mode by the monitoring company (Full System).
-
12th June 2026, RNO 5 Cloud 5 and 500's Fan Gallery's Pnuematic / Hydro Static Water Test Continuation Through the Weekend
ACCO's Pnuematic and Hydro Static Water test will be continuing through the weekend. That's all of could 5 and all relayed 500's fan galley's
Thank you for everyone's patients
Current Site Weather
Unavailable
Time Zone - Central Standard Time
Forecast - Sunday, 23 August
Unavailable
Tomorrow - Monday, 24 August
Unavailable
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enroll online at your convenience and save yourself time.
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enroll online at your convenience and save yourself time.