05th septembrie 2025, Cosco RNO 5 Fire Suppression Testing
Pneumatic testing of RNO5 fire suppression systems over power rooms 605, 606, 607, 407, 406, 405, 507, 508, 509 at 40psi from 9/6 2pm- 9/9 10am. These room will not be accessible for the duration of testing.
Anexe :
Power room 4 5 6 .pdf
Aboveground Test Cert copy .pdf
IMG_0383.jpg
Switch5 system 5&6.pdf
System 14.pdf
-
03rd septembrie 2025, RNO4 Area L Power Rooms Pressure Test 9/3/25
All - Please see below details for ACCO Pressure test to take place in RNO4 tomorrow 9/3/25.
Anexe :
Location: RNO4 Sector L Power Rooms (Vaults 7 & 8)
System: 10" Chilled Water Piping
Pressure: 150 PSI Hydrostatic
Test Duration: 3 hours (1 hour fill 2 hours test)
Exclusion zone will only prohibit work taking place above 10' from finished floor.
Exclusion starts: 9/3/2025 3:00PM
Exclusion expected end: 9/3/25 6:00PM
Sector L Test #L1 10 inch Markup Power Rooms.pdf
-
02nd septembrie 2025, REVISED RNO4 3pm Pressure Testing Power Room 605
Pressure testing will be at 3:00 PM in Power Room 605
Condiții meteo curente la șantier
Indisponibil
Fus orar - Ora standard orientală nord-americană
Prognoză - duminică, 14 septembrie
Indisponibil
Mâine - luni, 15 septembrie
Indisponibil
Cunoașteți cerințele EIP pentru acest șantier?
Asigurați-vă că aveți echipamentul de siguranță corect pentru prima zi la locație.
Începeți să lucrați mai devreme atunci când ajungeți în locație.
Finalizați înregistrarea la șantier online când doriți și economisiți timp.
Cunoașteți cerințele EIP pentru acest șantier?
Asigurați-vă că aveți echipamentul de siguranță corect pentru prima zi la locație.
Începeți să lucrați mai devreme atunci când ajungeți în locație.
Finalizați înregistrarea la șantier online când doriți și economisiți timp.