25th 四月 2025, 48 hour MVG 01/04 Energization
All
This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project. -
25th 四月 2025, 48 hour Energization notice
All
This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project. -
14th 四月 2025, PreTesting
There will be Pretesting for Strobes and Lights for Building 109. CSI is heading this up.
当前现场天气
不可用
时区 - 北美中部标准时间
预测 - 星期六、26 四月
不可用
明天 - 星期日, 27 四月
不可用