Amazon RIC6 - Herkese Açık Proje Sahası
-
25th Nisan 2025, 48 hour MVG 01/04 Energization
All
This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project. -
25th Nisan 2025, 48 hour Energization notice
All
This is a 48hr-energization notice informing everyone onsite at QTS NAL2 that we be energizing medium voltage gears 1 and 4 (MVG-01/04) in the Gen Yard on the west side of DC1 at 12pm on 04.28.25. The entire Gen yard and the substation will be a no work zone for all Unauthorized Personnel. Violation of any CAZ (controlled access zone) will result in immediate removal from the project. -
14th Nisan 2025, PreTesting
There will be Pretesting for Strobes and Lights for Building 109. CSI is heading this up.
Geçerli Saha Hava Durumu
Kullanılamaz
Zaman Dilimi - Kuzey Amerika Doğu Standart Saati
Tahmin - Cumartesi, 26 Nisan
Kullanılamaz
Yarın - Pazar, 27 Nisan
Kullanılamaz
Bu sahanın KKD Gereksinimlerini biliyor musunuz?
Sahadaki ilk gününüzde doğru güvenlik ekipmanlarına sahip olduğunuzdan emin olun.
Sahaya geldiğinizde kısa süre içinde çalışmaya başlamak için hazırlanın.
Saha kaydınızı çevrimiçi tamamlayın ve zamandan kazanın.
Bu sahanın KKD Gereksinimlerini biliyor musunuz?
Sahadaki ilk gününüzde doğru güvenlik ekipmanlarına sahip olduğunuzdan emin olun.
Sahaya geldiğinizde kısa süre içinde çalışmaya başlamak için hazırlanın.
Saha kaydınızı çevrimiçi tamamlayın ve zamandan kazanın.