05th 5月 2026, RNO4 Building in TEST MODE
RNO4 Building is in TEST MODE, please be cautious with debris, dust, or smoke that can potentially activate the FIRE ALARM SYSTEM.
-
03rd 5月 2026, Team, RNO4 Building is in TEST MODE please be cautious with debris, dust or smoke that can potentially activate the FIRE ALARM. Time: 6:30am to 2pm.
Team,
RNO4 Building is in TEST MODE please be cautious with debris, dust or smoke that can potentially activate the FIRE ALARM. Time: 6:30am to 2pm. -
02nd 5月 2026, ACCO Refrigeration test J line ( Admin).
ACCO REFER
添付ファイル :
Location: J-Line (Admin)
System: VCU 28 & 29
Test Pressure: Pneumatic 600
Exclusion Zone: 8 feet
Date: 5/2/26 – 5/3/26
Time: 3:30 PM – 3:30 PM (24 Hours)
Test Details
ACCO Refer will be performing a pneumatic test on VCU systems 28 & 29 starting at 3:30PM 5/2/26 until 3:30 PM 5/3/26 (24-hours). Test pressure will be 600 PSI with an exclusion zone of 8 feet.
Safety & Coordination:
For the safety of all personnel and to minimize disruptions, please ensure that all trades coordinate with onsite teams to relocate work activities for the duration of the test. Please see delineation map for routes around the testing zone.
acco testing 5.2.26.png