Amazon - CMH0 - Project Blue Marlin 2024 - 공공 프로젝트 현장
-
18th 3월 2026, RNO4 Fire Protection Systems Going Live
Team,
For everyone's awareness there is a final TCO Inspection today with the Fire Marshall at 15:00 for clouds 3 & 4 and power rooms 3 & 4. After said inspection systems will be fully live in a permanent state moving forward.
Again, this is for clouds 300 400 and the associated power rooms in RNO4 - please treat these as live systems moving forward. -
03rd 11월 2025, Stop work due to high winds
All roof work, outdoor elevated work, and crane activities must stop due to high wind speeds.
-
22nd 10월 2025, RNO4 VCU 39 pneumatic testing on 10/23/25
Safety team,
Please see below outlined bulletin for testing tomorrow and send to trades via bulletin.
Location: RNO4 admin area
System: Copper Refrigeration Lines
Pressure: 600 psi
Duration: 24 hours
Exclusion zone starts: 7:00 AM 10/23/25
Exclusion zone expected end: 8:00 AM 10/24/25
Acco Plumbing will be performing a pneumatic test in area 39, Test pressure is 600 psi for 24 hours hold time.
Please avoid these test area and barricades. Exclusion zones are barricaded and not to be crossed.