Permit Board - Project Mustang

Last Updated 4/4/2025 4:29:52 PM

Type
Employer
Location
Start
End
Status
PER-284141
Ground Disturbance Permit
HEI Civil
Brady Powers
+ 9 other supervisors
crane road south / Crane road south
6:31 AM
6:31 PM
Scheduled 9 hours ago
Roof Access Permit
U.S. Engineering Construction IENG Contractor
Alvis Wells
+ 11 other supervisors
Seq 2 / ASRS roof and Production roof
Phase 1A / ASRS roof and Production roof
+ 2 other zones
7:00 AM
4/5/2025
2:30 PM
4/5/2025
Pending Approval
Hot Work Permit
U.S. Engineering Construction IENG Contractor
Alvis Wells
+ 11 other supervisors
crane road south / North Boiler Room and U.S.E Connexes
Phase 1C / North Boiler Room and U.S.E Connexes
7:15 AM
2:00 PM
Awaiting Closeout
Roof Access Permit
U.S. Engineering Construction IENG Contractor
Alvis Wells
+ 11 other supervisors
Seq 2 / The roof
Phase 2/Office / The roof
+ 6 other zones
7:00 AM
2:00 PM
Expired 2 hours ago
Not Stopped