PER-398022
Structure Penetration Permit
MMR Construction, INC
Andres Figueroa ortiz
+ 30 other supervisors
Phase 10 Electrical Room / e room
Phase 11 Electrical Room / e room
5:55 AM
2:00 PM
In Progress
PER-395058
Request to Energize/De-energize
MMR Construction, INC
Andres Figueroa ortiz
+ 30 other supervisors
Phase 05 DAHU Gallery / JAN102 MSDB 1.4A1-3 Downstream
Phase 05 Electrical Room / JAN102 MSDB 1.4A1-3 Downstream
+ 1 other zones
2:00 PM
9/13/2025
9/13/2025
2:00 PM
Scheduled
21 hours ago
PER-395064
Request to Energize/De-energize
MMR Construction, INC
Andres Figueroa ortiz
+ 30 other supervisors
Phase 06 Electrical Room / JAN102 MSDB 1.5A1-3 Downstream
Roof / JAN102 MSDB 1.5A1-3 Downstream
+ 1 other zones
2:00 PM
9/13/2025
9/13/2025
2:00 PM
Scheduled
21 hours ago
PER-395060
Request to Energize/De-energize
MMR Construction, INC
Andres Figueroa ortiz
+ 30 other supervisors
Phase 05 DAHU Gallery / JAN102 MSDB 1.4B1-3 Downstream
Phase 05 Electrical Room / JAN102 MSDB 1.4B1-3 Downstream
+ 1 other zones
2:00 PM
9/13/2025
9/13/2025
2:00 PM
Scheduled
21 hours ago
PER-398050
Roof Access Permit
MMR Construction, INC
Andres Figueroa ortiz
+ 30 other supervisors
Roof / Phase 7
7:18 AM
2:18 PM
Scheduled
4 hours ago
PER-398052
Roof Access Permit
CSI
Anthony Ward
+ 3 other supervisors
Roof / over office PH1
Office / over office PH1
8:00 AM
2:30 PM
Scheduled
3 hours ago
PER-395065
Request to Energize/De-energize
MMR Construction, INC
Andres Figueroa ortiz
+ 30 other supervisors
Phase 06 Electrical Room / JAN102 MSDB 1.5B1-3
Roof / JAN102 MSDB 1.5B1-3
+ 1 other zones
7:00 AM
9/13/2025
9/13/2025
4:00 PM
Scheduled
1 day ago
Hot Work Permit
Mullins Mechanical
Aaron Morgan
+ 49 other supervisors
Phase 07 Gen Pad / Fuel tank and pump house
6:30 AM
9/13/2025
9/13/2025
3:30 PM
9/13/2025
9/13/2025
Expired
19 hours ago
Not Stopped
Roof Access Permit
MMR Construction, INC
Andres Figueroa ortiz
+ 30 other supervisors
Roof / east side of building
6:04 AM
9/13/2025
9/13/2025
4:04 PM
9/13/2025
9/13/2025
Awaiting Closeout